Official title of the project

Waste Water Treatment Project-Sabac

Project information

Region / City
Cities
Sabac
Total budget of programme / project

18135000

Implementation period
2011. May - 2013. Apr
Expected results

To protect and improve surface water quality of the River Sava by treating the collected and transported industrial and communal wastewater.

Beneficiary

Municipality Sabac

Summary of the project

Main Physical Project Components with brief Quantitative Indicators:

  • By-pass interceptor sewer, ending at the future wastewater treatment plant (o800mm, L=1950m).
  • Sewage pumping station (SPS) Glavna at the existing wastewater outlet (4 m3/s, 132 kW);
  • WWTP (wastewater treatment plant) – phase 1A for 84.000 population equivalent (PE).
  • River bank protection-reinforcement (1600 m).

Embedding in documented development strategies: National Strategy X; Regional Strategy X; Local Strategy X; Urban Master Plan X
Fact sheet - SR
Fact sheet - EN

Programme/Project objectives

  • To protect and improve surface water quality of the River Sava by treating the collected and transported industrial and communal wastewater. The project is in line with EU directives and with Serbian legislation and regulations.
  • Improve standard of service in wastewater collection.
  • Avoid pollution of both underground and surface waters, and serious health hazard by current use of sceptic tanks.